Sewerage & Drainage:Benefits from KEIIP work
Tranche 3 - Status of Implementation Progress*
Objective: These works will ensure improved sanitation services, enhanced wastewater treatment for Kolkata and resolve water logging issues
Ongoing works will ensure a flood-free, climate-ready Kolkata
- Total Nos. of Packages: - 10 nos. (4 completed)
- Scope at a Galnce
- Laying of Sewer line – 37.5 km (Completed 34.4 km)
- Construction of 3 STPs with a combined capacity of 108 MLD
- Construction of Pumping Station 5 nos. (All are put in operation)
- Laying of Pumping Main (Completed)
Improvement of S&D network and construction of pumping station in Alipore body guard line premises in Ward 74
- Contractor
- RG - Jyoti JV
- Date of Commencement : 20.11.2019
- Rev. Comp. Dt.: 15.12.2022 + O & M period (05 yrs.)/li>
- Contract Amount (INR): 39.59 (Works)+ 2.00(O & M)
Physical Progress
Main Components
- Development of S&D Network within BGL campus, ward 74-3.0 km
- Construction of Combined Cycle Pumping Station within BGL campus-SWF-3 working + 1 standby + 1 future, capacity 300 lps each, DWF-2 working + 2 standby, capacity 16 lps each
- Laying of SWF Pumping Main (1016 mm outer diameter) through National Library Avenue and Belvedere Road-1.2 km (Part to be laid by Micro tunneling method for 0.3 km and part to be laid by cut and cover method for 0.85 km and part to be laid by Jack pushing method for 0.05 km) and laying of DWF pumping main (200 mm dia.)-30 m
Construction of Sewage Treatment Plant near WBSETCL, Joka
- Contractor
- M/s SNET-SSG JV
- Date of Commencement : 08.03.2019
- Date of completion 02.09.2021+ O & M period(05 yrs.)
- Revised Date of completion 30.06.23+ O & M period (05 yrs.)
- 2nd Revised Date of completion 30.06.2025+ O & M period (05 yrs.)
- Contract Amount (INR): 78.17 (Works)+ 4.35 (O & M)
- Revised Contract Amount (INR): 87.30 (Works)+ 4.35 (O & M)
Physical Progress
Main components
- The proposed STP will cater to the DWF generated from wards 125, 126, 144 and parts of ward 123, 124 and 143 under Borough XVI and 127 (Borough XIV). The population of the catchment for the design horizon (2030) is 2,57,882 and its total catchment is approximately 1444 Ha, which will serve as the command area for the proposed STP.
- The site of the proposed STP is located off the Diamond Harbour Road in ward no. 144 in South Kolkata primarily identified as Joka, the complete command area of the WBSETCL STP
Construction of Sewage Treatment Plant at Bank Plot, MG Road, Joka
- Contractor
- M/s SNET-EAGLE INFRA JV
- Date of Commencement : 08.03.2019
- Revised Completion Dt. 30.06.23 + O & M period (05 yrs.)
- 2nd Revised Completion Dt. 30.12.25 + O & M period (05 yrs.)
- Contract Amount (INR): 70.31 (Works) + 4.15 (O & M) for 5 years
- Revised Contract Amount (INR): 76.67 (Works) + 4.15 (O & M) for 5 years
Physical Progress
Main components
- Construction of STP ( capacity - 40 MLD )
- Area Coverage: Ward –122 (Part), 123 ( Part), 124 (Part), 142, 143 ( part), 144 ( Part)
- Purpose: For treatment of wastewater, generated from the above wards, to the environmentally sustainable levels
- Population Benefited: 2,61,000
Construction of 23 MLD sewage treatment plant at Rajpur- Sonarpur, Rania including O & M for 15 years
- Contractor
- M/s TEPL- SNET JV
- Date of Commencement : 04.05.2021
- Revised Date of completion : 31.07.23(O & M)
- 2nd Revised Date of completion : 31.03.2025 (O & M)
- Contract Amount (INR): 63.27 (Works)+ 5.53 (O&M)
- Revised Contract Amount (INR): 70.34 (Works)+ 5.53 (O&M)
Physical Progress
Main Component
- Construction of 23 MLD sewage treatment plant at Rajpur- Sonarpur, Rania including O & M for 15 years
- Population Benefited:166,000



